July 01

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed

Observations

Normal startup today.

Antenna availability: automatic assessment.

July 02

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed

Observations

Normal startup today.

Antenna availability: automatic assessment.

July 03

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed

Observations

Normal startup today.

Antenna availability: automatic assessment.

July 04

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
The 27mgot stuck last night. The problem was fix in the morning.
13 Ant13 is showing poiting erros along the day.

Antenna availability: automatic assessment.

July 05

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
Normal startup today / The 27m got stuck in the LO during most of the calibrations

Antenna availability: automatic assessment.

July 06

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
Normal startup today
3 Ant3 got stuck in EL. $pcycle at 15:28UT / Manlight and ROACH problems around 17:30UT, no useful data after that

Antenna availability: automatic assessment.

July 07

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
New delays were set.
13 Ant13 pointing tests along the day.

Antenna availability: automatic assessment.

July 08

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
Normal startup today.
13 Ant13 pointing errors.
3 Ant3 got stuck in the morning, $pcycle at 14:25 UT.

Antenna availability: automatic assessment.

July 09

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
Normal startup today.
13 Ant13 pointing correected on Windows machine at 14:00 UT.
13 Ant13 software updated at 16:15 UT
7 Ant7 got stuck in AZ $pcycle 00:50 UT

Antenna availability: automatic assessment.

July 10

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed
Normal startup today.
7 Ant7 got stuck in AZ on the PHASECAL at 23:14 UT. / $pcycle at 23:53 UT

Antenna availability: automatic assessment.

July 11

Configuration: ATA feed is on Ant6.

Issues and outages

Time (UT) Antennas Details
2 Ant 2 still out with Dec controller problem.
13 Jun 3: Ant13 is down due to the solar power station charger having failed. / The manufacturer has been contacted to see about repair or replacement.
11 Jun 17: Ant11 FEM LNA failed

Observations

Normal startup today.

Antenna availability: automatic assessment.